Havre des Pas Resurfacing work has resumed.
It was suspended last week because technical issues at the Ronez manufacturing plant meant asphalt couldn't be supplied.
Work that didn't need asphalt has continued since.
A government spokesperson says, as things stand, the project should finish before the end of this month as scheduled.
The work started on 10 January.

Concerns were raised in the last States sitting about the disruption this work was causing.
Infrastructure Minister Deputy Kevin Lewis said the work was planned in the early months of the year as traffic figures demonstrated that it was the quietest period for the road network and have the least impact on the bus network.

Eyes up! It's Air Display day...
Haut Du Mont Trial: 'It could explode', jury hears 999 calls
Haut Du Mont Trial: Worker checking gas valves spent almost 'entire' time on his phone
Red Arrows still expected for Jersey Air Show
Haut Du Mont Trial: Gas works were 'sloppy, unsafe, and cut corners', allege prosecutors
26 Victoria Village homes get planning permission
Haut du Mont trial: Explosion 'an incident waiting to happen'
Jersey flights impacted by UK air traffic control issue