The new premises of The Guernsey Institute at Les Ozouets is taking shape, just 10 months ahead of welcoming its first cohort of students.
The exterior of the upcoming Les Ozouets campus is in place.
Inside, there are concrete corridors, empty rooms, plastic coverings over window gaps, and a few pipes and wires waiting to be fitted.
The near-£62 million development is being led by Channel Island construction company Rok.
It's designed to accommodate 5,000 students and bring all the vocational courses from the Institute’s three current sites together under one roof - everything from early years training to plumbing and the creative arts.
Island FM joined a media tour of the site today (20 November) to see the progress.
On this tour, President of Education Deputy Paul Montague said he is keeping his fingers crossed that the project stays on track.
"We are currently on budget and on time.
"But I have to be reasonably cautious about that.
"There's many a slip, twixt the cup and the lip. (Meaning things can still go wrong)
"Even today you can see the flooding in some parts of the site which does delay some of the progress and some of the external works."
Deputy Montague added that this kind of investment is overdue.
"I have a colleague who went to Delancey to teach there, and originally he was told, don't worry, you're only going there for two years, and actually he's been there 17 years now.
"So I am pleased that finally Guernsey has pulled its finger out, invested in infrastructure for our young people and particularly infrastructure that's so valuable for the economy going forward."
Head of education capital projects Ash Dupre says they've been battling the bad weather.
"Hopefully by Christmas we'll be 100% watertight, if not a couple of per cent off that.
"We've got another forecasted horrific winter to come through.
"We have been very pragmatic, and part of our mitigation planning since last winter is working extensively with Rok over this, the last sort of eight months in particular, and we've re-planned a lot of the work.
"So there's a lot more work going on now than there was originally planned, and that was in light of the bad weather that we had last year."
Mr Dupre hopes this campus will benefit future generations of islanders.
"This is really going to be a game-changer.
"It will be absolutely purpose-built, fit for purpose, amazing facilities.
"Those students coming through should be, I'm sure, very, very happy to be working here."
Building works for the Sixth Form Centre and sports facilities have been allocated to Phase Two of the programme.

Guernsey to benefit from UK-EU trade deal
New lifesaving equipment at Guernsey's bathing pools
11% of Guernsey households 'often cannot afford essentials'
Guernsey's Deputy Bailiff announced as Megan Pullum KC
Gas company appoints new safety boss
Girls in Guernsey lag behind boys in physical activity levels
Guernsey road users still ignoring road works signs
Guernsey game shop 'exceptionally' busy ahead of GTA 6 release